Vancouver measures its 2 m screen from the site boundary. White Rock uses 4 m from the lot boundary in its definition of an off-site tree. New Westminster starts its 4 m construction trigger at a protected tree’s dripline.

The three distances are not interchangeable.

Vancouver Starts at the Site Boundary

If your excavation is planned beside the site boundary, start there. Vancouver’s Protection of Trees By-law No. 9958 looks for each retention tree on the project site, on adjacent property within 2 m of the site boundary, and on a street adjacent to the site. The required protection barrier must be in place before demolition, excavation or construction begins.

The phrase “within 2 m” needs its noun. It’s 2 m from the site boundary for an adjacent-property retention tree. That boundary measurement does not say every neighbouring tree within that distance needs a removal permit. The barrier must be inspected and approved by the Chief Building Official before a demolition, excavation or construction permit issues.

Once an adjacent-property retention tree falls inside that boundary screen, the barrier extends into the project site. Its extent is the greater of 2 m or another distance set by an arborist or the Director of Planning.

The barrier is also part of Vancouver’s permit gate. The Chief Building Official must inspect and approve the applicable barriers on the site or adjacent property. The City Engineer handles inspection and approval of street barriers. The bylaw ties those inspections and approvals to entitlement to the demolition, excavation or construction permit.

The Vancouver permit guide covers the city’s broader application rules. Our Schedule A barrier article covers Vancouver’s trunk-diameter table.

Vancouver Treats Street Trees Separately

A tree beside the street adds a separate check. Before a boulevard or lane tree is pruned, moved or otherwise disturbed, Vancouver requires prior written Park Board permission.

Each applicable barrier must stand at least 0.6 m from a curb. If a sidewalk sits within a grass boulevard, the applicable barrier must stand at least 0.3 m from the sidewalk edge.

White Rock Defines an Off-Site Tree

In White Rock, the boundary distance starts with a definition. The Tree Protection Bylaw, 2021, No. 2407 defines an off-site tree as any tree within 4 m of the lot boundary. That definition alone doesn’t say every tree within 4 m is protected, needs a removal permit, or controls the construction envelope.

The protected area, called the CRZ or TPZ, is a separate piece of the rule. White Rock defines them as the same zone, with a radius equal to the greater of 6 times DBH or 1 m beyond the dripline.

Then there is the barrier itself. White Rock calls for a barrier at least 1200 mm high, with 50 by 100 mm wood posts set 450 mm deep at no more than 2 m spacing. The printed detail also specifies top and bottom rails, plastic mesh, the tree centred, 300 mm from paving and 600 mm from curbs.

If you’re preparing a White Rock file, keep the White Rock permit guide beside the plan rather than carrying over a detail from Vancouver.

New Westminster Measures From the Dripline

In New Westminster, the starting point moves again. The 4 m construction check doesn’t start at the trunk or property boundary. Section 8.1 of Tree Protection and Regulation Bylaw No. 7799, 2016 measures it from a protected tree’s dripline. Work within 4 m of that dripline requires a barrier plus permit, or a standalone CRZ work authorization.

The actual CRZ has its own formula. New Westminster defines the CRZ and TPZ as the same zone, with a radius equal to the greater of 6 times DBH or 1 m beyond the dripline.

Measure the 4 m from the dripline, not from the trunk or the lot boundary.

The New Westminster permit guide has the rest of the city’s permit path.

Write Down Where Each Distance Starts

Before design work moves ahead, write down the municipality, the measured object and the applicable distance. For these three municipalities:

  • Vancouver: an adjacent-property retention tree within 2 m of the site boundary, followed by an on-site barrier extent of at least 2 m or a greater set distance.
  • White Rock: an off-site tree within 4 m of the lot boundary, with a separate CRZ and TPZ radius formula.
  • New Westminster: work within 4 m of a protected tree’s dripline, with a separate CRZ formula.

Construction Reports in Metro Vancouver

Our BC construction arborist report service prepares ISA Certified Arborist reports for Metro Vancouver permit applications. We confirm availability for your address before we quote. Contact us with the site address and a short description of the planned work.

Reply Within 24 HoursSubmit below or email vancouver@arboristgroup.com

Get a quote

Tell us about your property. An ISA Certified Arborist will reply with a firm quote.

  • Free consultation, response within 24 hours.
  • We confirm availability for your address before we quote.
  • We do not sell tree removal.

ISA Certified Arborist  ·  ISA Member

Get Your Free Consultation

Service Needed